Possible new schedule
Anne still has not received anything in writing, but this is what she was verbally told about the new time schedule:
May 14 begin the inter phase, we will discuss what days we will be open half days to move staff, computers and collections during this time period
June 24 possible last day of inter phase, must be off of 2nd floor, must have 3rd floor ready for services
June 25 first day of Phase II - renovation of 2nd floor
Dec 15 possible last day of Phase II
Dec 16 possible first day of inter phase
Jan 27, 2008 possible last day of inter phase, must be off of 1st floor, want to have 2nd floor restored for services if possible
Jan 28 possible first day of Phase III
June 30 possible last day of Phase III
July 1 possible first day of Mookini Library trying to shelve all materials in permanent place, house staff in permanent locations
November 30, 2008 renovation complete?