Sunday, February 11, 2007

Revised Dates

Revised dates for construction:

Phase 1 (3rd floor) - December 18, 2006 to May 6, 2007

Phase 2 (2nd floor) - June 25, 2007 to December 7, 2007

Phase 3 (1st floor) - January 28, 2008 to June 30, 2008

There is the possibility that the completion dates will change as the project moves on...